STORMWATER PROGRAM


Download (115k) the Stormwater Phase II Final Rule - Small M24 Stormwater Program Overview.



Task Completion Date
Prepare a draft SWMP with BMPs that reflect current County operations and goals January 30, 2009
Prepare a Monitoring / Assessment Plan that's coordinated with the draft BMPs, address the TMDL, as was required in the First Annual Report by Part 5.6 of general permit February 20, 2009
Complete the ESA and NHPA eligibility evaluations February 20, 2009
Perform an internal review of the draft SWMP, and prepare it and the NOI for public notice March 30, 2009
Issue public notice of the SWMP and NOI being available for public review April 13, 2009
Respond to public comments and make final revisions to the SWMP June 12, 2009
Sign and certify the NOI and SWMP, and submit them with attachments to EPA June 30, 2009